PHOTO GALLERY

 

Pipelines of Refineries of a leading Taiwanese Oil Company


 

Power tool cleaning using grinding stone to remove loosely adhering rust and existing coating.  It also needs to create a certain degree of roughness on the surface to enhance mechanical anchor of coating on the substrate. The 16” O.D pipe was provided by Chinese Petroleum Corp. (CPC)

 

Artificial defect dimensions as marked on the pipe spool # 2 (length – 150mm, width –6.5mm, depth – 9.45mm)

 

Take  measurements of pipe spool #1 anomaly (artificial defect) with a vernier caliper and depth micrometer

 

 

 

 

Preparation of pressure gage equipment for pipe spool # 1

 

Fill up the anomaly (artificial defect) with Corro-Dur 561 FS up to the level of the original external pipe wall of pipe spool #2.

 

After filling the defect area, Corro-Dur 561 FS was applied over the pre-determined length of repair

 

 

 

Continue application of Corro-Dur 561 FS on the underside portion of the pipe

 

The first roll of Corro-Wrap (size of roll 6” x 30’)  is being used to wrap the pipe

 

During the wrapping process, water is sprayed on the Corro-Wrap and the pipe.

 

 

 

 

After the first roll of Corro-Wrap was used, a perforated shrink wrap was wrapped around the pipe to give it a snug fit.

 

After a few minutes, the shrink wrap was removed to continue application of the required number of rolls

The wrapping is completed and water was sprayed on the entire area to complete reaction of Corro-Wrap

 

 

 

 

Both test spools are now ready for testing.  Pipe spool # 1 (without the wrap) is subjected to hydrostatic pressure testing.

 

Pipe Spool # 1 artificial defect area has ruptured at 125 kg/ sq.cm. and pipe spool # 2 is also subjected to hydrostatic pressure testing which will be maintained at 70 kg/sq.cm for 24 hours

 

The next day, pipe spool # 2 pressure printout shows that it almost reach 105 kg/sq. cm but went down to 62 kg/ sq. cm due to expansion and contraction of the material (pipe and water).  At the same time it was observed that there was a leak on the pipe fitting which affected the pressure readings.

 

 

 

 

This part of the fitting that exhibits the leak is connected to the pressure  gage printout instrument

 

The printout didn’t give an accurate data due to the leak in the fitting and so it was decided to do a re-testing of pipe spool #2.

 

The water in the pipe was removed and it will be transferred inside the warehouse so as not to be affected by temperature changes.

 

 

 

 

Continue draining water from the pipe

 

Attach all the necessary fittings and instruments prior to re-testing

 

Set the printout gage at 70 kg/sq.cm which shall be maintained  for another 24 hours.

 

 

 

 

 

 

 

The entire set up was completed for re-testing of pipe spool # 2.  Corro-Wrap finally passed CPC’s testing  when it has maintained its pressure at 81kg/sq.cm., then it was increased to 105 kg/sq. cm. and maintained  for 30 mins.  Afterwards, the pressure was increased and the pipe ruptured or showed signs of leakage at 145 kg/ sq. cm. which is way beyond the designed pressure